Energy workers plan to perform transformer maintenance and equipment replacement, which will require temporary power outages in certain parts of the city.
Outage schedule in the Eastern RES
- 7th microdistrict, residential buildings No. 9, 10, 11, 12 (TP-608) — from 09:30 to 12:00 (maintenance)
- Vostok-5 microdistrict, residential buildings No. 3, 4, 7, 8, 11, 12, 13, 14, 25 (TP-82) — from 09:30 to 15:00 (transformer replacement)
- Sechenov, Perekopskaya, Botalieva, Tynystanova streets (TP-965) — from 10:00 to 13:00 (meter installation)
- 7th microdistrict, building No. 12/1 (TP-1009) — from 11:00 to 14:00 (maintenance)
- Musa Jalil, Yaltinskaya, Zapadnaya streets, Jibek Jolu Avenue, Kurmanjan Datka (TP-472) — from 13:00 to 17:00 (transformer replacement)
- Chernyshevsky, Gvardeysky, Elebaev streets (TP-2440) — from 14:00 to 16:30 (maintenance)
Outages in the Western RES
- Archa-Beshik residential area (Kambar-Ata St., Ak-Tan, TP-2404) — from 09:00 to 12:00 (250 A circuit breaker installation)
- Archa-Beshik residential area (Kuyukova St., Bereke, TP-2220) — from 09:00 to 13:00 (circuit breaker replacement)
Context
The works are being carried out by the Bishkek Electric Grid Enterprise to ensure the stable operation of the city's power system.