What happened
Active work is underway to provide electricity to the infrastructure of the Ala-Too Resort all-season tourist complex. According to the Issyk-Kul Electric Grid Company, most major facilities have already gained access to the power supply. Specifically, electricity has been supplied to four cable car stations (designated as A, C, E, and X), as well as to the meteorological and avalanche stations. Additionally, power has been provided to the administrative building of the ski equipment rental point, as reported by Tazabek and Kabar.
According to data from OJSC National Electric Grid of Kyrgyzstan (NESK), the installation of 10 transformer substations of various capacities—630, 1,000, and 2,000 kVA—is planned to ensure the stable operation of the entire complex. To date, the installation of nine units has been completed. The final, tenth substation is scheduled to be installed by November 25. Alongside the substation installation, work continues on laying cable lines and connecting other areas of the complex to the grid.
Technical details of the work include the laying of cable lines of various lengths. According to Tazabek, approximately 1.4 km of 0.4 kV cable line was laid to the stage, and six distribution devices were installed, after which electricity was supplied to the site. Approximately 2 km of 0.4 kV cable has also been laid within the yurt camp area. Cable lines have been run to administrative and utility buildings and local treatment facilities. Currently, energy workers are continuing work to connect wooden houses, the yurt camp, and other complex facilities.
Who is involved
Rustam Sakiev, General Director of OJSC National Electric Grid of Kyrgyzstan, participated in a working trip to the Issyk-Kul region on November 22, during which he inspected the progress of work at the sites. According to Tazabek, he instructed the responsible departments to complete all work within the established deadlines to ensure the reliability of the power supply. Sakiev also visited a training center where specialists are trained to work on electrical equipment under voltage without disconnecting the electricity. This center was established following an instruction from the President, and the project is being implemented under the personal supervision of the Minister of Energy.
The numbers
The complex requires the installation of 10 transformer substations with capacities of 630, 1,000, and 2,000 kVA, 9 of which are already installed. The deadline for installing the final substation is November 25. Regarding cable work, 1.4 km of 0.4 kV line has been laid to the stage, and approximately 2 km of cable with the same voltage has been laid in the yurt camp. To connect additional facilities, such as floodlights on the ski slopes and the food court, 12 more distribution boards are planned: 10 for slope lighting and 2 for the food court area. The total number of media publications regarding this event amounted to 3.
What comes next
The installation of the final, tenth transformer substation is expected to be completed in the near future, specifically by November 25. Following this, power supply work will continue for the yurt camp, wooden houses, and other complex facilities.
Plans also remain to install 12 distribution boards to connect floodlights on the ski slope and the food court. Questions remain regarding the exact completion dates for connecting the wooden houses and the full operational readiness of all complex zones.
Sources
This analysis was prepared by the news.kg newsroom from published material — our own articles and the reports by the outlets listed below. All facts and figures come from them.
- Nine transformer substations installed at Ala-Too Resort in Issyk-Kul region — news.kg
- «Ала-Тоо Резортто» 9 трансформатор орнотулду — Эркин-Тоо
- Для «Ала-Тоо Резорт» установили 9 трансформаторных подстанций — Кабар (рус.)
- На «Ала-Тоо Резорт» обеспечили электроснабжение четырех станций канатной дороги — Tazabek