The state enterprise Kyrgyzkurulush, operating under the Ministry of Construction, Architecture and Housing and Communal Services, is currently managing the construction project in the Issyk-Kul region.
Current construction progress
According to the Ministry of Construction, Architecture and Housing and Communal Services, construction and installation works began in May of this year. Design works are being carried out in parallel with the building process.
As of now, the construction of the foundation has been fully completed, and the concreting of the first-floor slab is finished. Workers are currently installing support posts to set up the formwork for the second floor.
Context
The project is being implemented in Karakol, a city in the Issyk-Kul region with a population of approximately 85,588 people as of 2022.