What happened
On November 26, 2026, the first meeting of the Kyrgyz-Chinese working group on electric power in a "government-to-enterprise" format was held in the Chinese city of Qingdao, according to the press service of the Ministry of Energy of the Kyrgyz Republic. The meeting was co-chaired by Kyrgyzstan's Minister of Energy Altynbek Rysbekov and the head of China's National Energy Administration Wang Hongzhi. The key discussion topic was the construction of a cross-border power line that will allow electricity to be imported from China to Kyrgyzstan, reports 24.kg.
According to the publication Erkin-Too, meeting participants also focused on the electricity supply for an industrial park located in the border zone and the prospects for integrating the power grids of the two countries. During the meeting, an official ceremony was held to exchange copies of the interagency agreement on cooperation in the electric power sector. As 24.kg and Knews.kg note, this document was signed earlier, on September 23, 2026. The parties exchanged information on the current state and development directions of the electric power industries, and also discussed the technical and organizational aspects of implementing the planned projects.
According to Kaktus.media, within the framework of the meeting, the parties identified priority tasks for further cooperation. Kyrgyzstan's Minister of Energy Altynbek Rysbekov stated that the ministry has nearly completed the development of financing mechanisms for the necessary energy infrastructure. A phased schedule was proposed for the project implementation, according to which the commissioning of the facility for industrial operation is planned for December 2027. According to Tazabek, meeting participants also reviewed technical issues necessary to ensure the operation of the future infrastructure.
Background
In August 2026, PRC President Xi Jinping made a state visit to Kyrgyzstan, during which agreements were reached that formed the basis for the current energy arrangements, reports 24.kg and Knews.kg.
Earlier, on August 10, 2026, a need for external electricity imports to cover the expected deficit during the 2026-2027 autumn-winter period was identified at a meeting of the republican headquarters in Kyrgyzstan, according to materials on winter season preparations.
Additionally, on August 11, 2026, it was reported that Kyrgyzstan is ready to export energy to Pakistan through the CASA-1000 project, which connects the power grids of Central and South Asia.
Who is involved
Representatives of the Kyrgyz Republic and the People's Republic of China participated in the working group meeting. Kyrgyzstan was led by Minister of Energy Altynbek Rysbekov. He emphasized the importance of the practical implementation of the agreements reached by the leaders of the two countries during Xi Jinping's visit in August 2026.
On the Chinese side, the meeting was chaired by the head of China's National Energy Administration Wang Hongzhi. Meeting participants represented government structures and enterprises in a "government-to-enterprise" format.
The numbers
The project involves commissioning the energy infrastructure for industrial operation in December 2027. Previously, on September 23, 2026, an interagency agreement on cooperation in the electric power sector was signed. According to the editorial office, 9 publications reported on this event.
What comes next
The project is planned to be implemented in the near future according to the proposed phased schedule. Kyrgyzstan's Minister of Energy Altynbek Rysbekov invited Wang Hongzhi to visit Kyrgyzstan on an official visit to hold the second meeting of the joint working group in Bishkek, reports Kaktus.media.
The specific volume of imported electricity and the exact parameters of the cross-border power line remain questions for which the materials do not yet provide an answer.
Sources
This analysis was prepared by the news.kg newsroom from published material — our own articles and the reports by the outlets listed below. All facts and figures come from them.
- Kyrgyzstan and China plan to build power lines for electricity imports by December 2027 — news.kg
- Кыргызстан готов экспортировать энергию в Пакистан благодаря проекту CASA-1000 — news.kg
- В Кыргызстане ожидается дефицит электроэнергии зимой: власти определили объемы импорта — news.kg
- Кыргызстан и Китай обсуждают объединение энергосистем двух стран — Knews.kg
- КР и Китай намерены построить ЛЭП для импорта электроэнергии к декабрю 2027 года — 24.kg
- С Китаем обсудили строительство ЛЭП для импорта электроэнергии в Кыргызстан — Kaktus.media
- Минэнерго предложило запустить ЛЭП для импорта электроэнергии из Китая в декабре 2027 года — Tazabek
- Кыргызстан и Китай планируют объединить энергосистемы — Sputnik Кыргызстан
- Кыргызстан и Китай планируют объединить энергосистемы — Vesti.kg
- Кыргызстан и Китай планируют объединить энергосистемы — Короче, KG
- Кыргызстан менен Кытай энергетика тармагындагы кызматташтыкты кеңейтет — Эркин-Тоо
- Какой масштабный энергетический проект готовят Кыргызстан и Китай? — Номад ТВ (YouTube)