The unstable heat supply was caused by repeated trips of a circuit breaker at a transformer substation under the responsibility of the Vostochny RES. According to the Bishkek City Hall, the equipment could not handle the electrical load, leading to system failures.
Outage schedule and measures taken
To resolve the issue, specialists from MP Bishkekteploenergo carried out replacement works on the faulty device. A new circuit breaker was installed at the substation between 11:00 and 12:20. Currently, the area's heat supply is operating normally.
The agency noted that MP Bishkekteploenergo ensured timely heat supply, and all necessary measures were taken to stabilize the equipment's operation.
Context
Bishkek is the capital of Kyrgyzstan, with a population of approximately 1.19 million people as of 2025.