According to the procurement portal, on November 11, OJSC Kyrgyz Agroholding, a subsidiary of the Ministry of Agriculture, announced the procurement of a stage of construction and installation works for the engineering part of a potato storage facility. The project is being implemented in the village of At-Bashy.

Scope of work and implementation timelines

The upcoming works cover a complex of engineering systems and site improvement. The following areas are included in the schedule:

  • laying of water supply and sewage lines
  • installation of heating and ventilation systems
  • installation of fire alarms
  • organization of power supply and installation of a transformer substation
  • outdoor lighting, installation of water tanks, and site improvement
23,076,000som (procurement amount)
21days (execution period)
24months (warranty period)

Context

OJSC Kyrgyz Agroholding is a subsidiary of the Ministry of Agriculture of the Kyrgyz Republic. The works are scheduled to be carried out in the village of At-Bashy.