According to the procurement portal, on November 11, OJSC Kyrgyz Agroholding, a subsidiary of the Ministry of Agriculture, announced the procurement of a stage of construction and installation works for the engineering part of a potato storage facility. The project is being implemented in the village of At-Bashy.
Scope of work and implementation timelines
The upcoming works cover a complex of engineering systems and site improvement. The following areas are included in the schedule:
- laying of water supply and sewage lines
- installation of heating and ventilation systems
- installation of fire alarms
- organization of power supply and installation of a transformer substation
- outdoor lighting, installation of water tanks, and site improvement
Context
OJSC Kyrgyz Agroholding is a subsidiary of the Ministry of Agriculture of the Kyrgyz Republic. The works are scheduled to be carried out in the village of At-Bashy.