On November 24, the relevant Jogorku Kenesh committee approved a draft agreement between Kyrgyzstan and the European Bank for Reconstruction and Development (EBRD). The total financing will amount to 1 billion euros, which is 2.5 times the previously agreed amount of 400 million euros, reported Deputy Finance Minister Nurbek Akzholov.

StoriesKyrgyzstan takes 1 billion euros from EBRD without expenditure breakdownSlides: 6
  1. Kyrgyzstan takes 1 billion euros from EBRD without expenditure breakdown
  2. Financing structure: 220 million euros — grant; 780 million euros — loan
  3. 542 million euros — amount with no specific projects in the documents
  4. «Does this mean that after the framework agreement is approved, the Jogorku Kenesh will not know what the remaining money was spent on?» — Dastan Bekeshev
  5. Funds already allocated for: 176 million euros for water projects in 13 cities; 75 million euros for energy projects in Balykchy; 45 million euros for the Kara-Balta — Chaldovar road; 45 million euros for irrigation in the Ak-Suu district
  6. The Ministry of Finance promises to submit projects for committee approval, but MPs demand this be officially formalized.

Allocation of funds and transparency issues

According to the Ministry of Finance, out of the total 1 billion euros, 220 million euros will be a grant, and 780 million euros will be a loan. The funds are planned to be directed toward infrastructure development, road construction, wastewater treatment facilities, and providing citizens with drinking water.

220million euros (grant)
780million euros (loan)
1billion euros (total)

During the discussion, MP Dastan Bekeshev pointed out that specific projects are only outlined in the documents for 458 million euros. The remaining 542 million euros are designated in the documentation as 'Other'.

"Does this mean that after the framework agreement is approved, the Jogorku Kenesh will not know what the remaining money was spent on?"
Dastan Bekeshev, MP of the VIII convocation of the Jogorku Kenesh

In response, Nurbek Akzholov assured that the department would submit projects for committee approval. However, Bekeshev insisted that this requirement must be officially recorded in the committee's decision.

Funds already allocated for

Part of the funds already has a designated purpose within current programs:

176million euros (water projects in 13 cities)
75million euros (energy projects in Balykchy)
45million euros (Kara-Balta — Chaldovar road)
45million euros (irrigation in the Ak-Suu district)