The new detention center is situated outside the capital to replace the aging institution on Kulatov Street. The facility was built on the territory of the former GSIN institution No. 50.
Facility capacity and infrastructure
The new complex covers a total area of 24,000 square meters. It is designed to accommodate 1,500 accused individuals. To facilitate legal proceedings, the facility includes four halls for mobile court sessions, a consultation room for judges, and separate offices for prosecutors and lawyers.
Key facility statistics
In addition to the detention blocks, the site includes a residential complex for staff consisting of two buildings with 48 apartments. The infrastructure also features a gym, an outdoor sports ground, and a parking area.
Construction timeline
According to Arzymat Rakhym uulu, the head of the Construction Objects Directorate, the project was completed following a two-year construction period.
- 2023
Project design phase began
- 2024
Construction works commenced
- November 25
New SIZO-1 officially opened