What happened
Construction of a large-scale sports complex for the B. Turusbekov Kyrgyz State Academy of Physical Culture and Sports has begun in Bishkek. According to reports by 24.kg, Kaktus.media, and Kabar, the work is being funded by the Stabilization Fund. According to the architectural design, the total area of the future facility will be 12,000 square meters. Construction work at the site is being performed by the state enterprise "Kyrgyzkurulush." Currently, builders have completed the excavation stage and have begun pouring concrete and concreting structures.
The complex's infrastructure includes an indoor swimming pool of 1,250 square meters, which, according to the press service of the Ministry of Construction, Architecture, and Housing and Communal Services of the Kyrgyz Republic, will meet Olympic standards. The facility will also include a training pool and a spectator stand with a capacity of 560 seats. The project is focused on creating conditions for high-quality athlete training and the development of the country's sports industry.
In addition to indoor facilities, the academy grounds will feature outdoor sports zones. The outdoor infrastructure will include a football stadium, two mini-football pitches, two basketball courts, and one beach football court. According to the materials, the new infrastructure is being created in accordance with modern architectural requirements and international standards, which will improve conditions for athlete training in the capital.
Background
The history of sports infrastructure development in the country includes several parallel projects. Previously, on October 29, 2026, it was reported that a new football base for Premier League clubs would be built in the village of Leninskoe near Bishkek. This facility is part of a large-scale project to build eight modern training complexes for Premier League clubs, with completion planned for next year.
Additionally, on October 30, 2026, reports emerged regarding the start of construction of a large sports town in the Kashka-Suu microdistrict of Karakol. The 12-hectare project is also funded by the Stabilization Fund. This sports town will include a sports boarding school, an Olympic-sized swimming pool, and a multifunctional complex. Thus, the construction of the academy complex in Bishkek is taking place alongside the implementation of other major infrastructure programs in the regions and the capital.
Who is involved
Several parties are involved in the implementation of the project. The primary client and recipient of the facility is the B. Turusbekov Kyrgyz State Academy of Physical Culture and Sports, which has a 70-year history. The construction work is being directly performed by the state enterprise "Kyrgyzkurulush."
Information regarding the construction progress and project parameters was provided by the press service of the Ministry of Construction, Architecture, and Housing and Communal Services of the Kyrgyz Republic. Financial support for the project is provided by the Stabilization Fund, from which the construction is being financed. The process is taking place in Bishkek, which has a population of approximately 1.19 million people as of 2025.
The numbers
According to the data presented, the total area of the new sports complex will be 12,000 square meters. The building will house an indoor swimming pool of 1,250 square meters meeting Olympic standards, as well as a 560-seat grandstand.
The list of outdoor areas includes two mini-football pitches, two basketball courts, and one beach football court. The total number of publications regarding this event in the provided materials is 3. The project is funded by the Stabilization Fund; however, the Ministry of Construction, Architecture, and Housing and Communal Services of the Kyrgyz Republic did not specify the exact total construction cost.
What comes next
At present, construction is at the concrete pouring stage following the completion of excavation. The materials do not specify exact deadlines for the completion of all construction work or the date the facility will be commissioned.
Questions remain regarding the total cost of the project and the exact schedule for completing construction stages, as the Ministry of Construction, Architecture, and Housing and Communal Services of the Kyrgyz Republic has not provided this information. Moving forward, work is expected to continue on concreting structures and erecting the academy's infrastructure.
Sources
This analysis was prepared by the news.kg newsroom from published material — our own articles and the reports by the outlets listed below. All facts and figures come from them.
- В Бишкеке строят новый спортивный комплекс для Академии физкультуры и спорта — news.kg
- В Караколе возводят спортивный городок на 12 га с интернатом и олимпийским бассейном — news.kg
- Под Бишкеком возводится новая футбольная база для клубов Премьер-лиги — news.kg
- Для Академии физической культуры и спорта в Бишкеке строят спортивный комплекс — 24.kg
- В Бишкеке для Академии физкультуры и спорта строят современный спорткомплекс — Кабар (рус.)
- В Бишкеке идет строительство спорткомплекса с бассейном олимпийского стандарта — Kaktus.media