The development of transport corridors will require significant track modernization and increased capacity, Uzbek President Shavkat Mirziyoyev announced during a meeting with transport and logistics industry representatives, according to the republic's press secretary Sherzod Asadov.
Freight Growth Forecast
The launch of the international corridor through Kyrgyzstan will lead to a tenfold increase in transport volumes. It is expected that between 15 and 16 million tons of cargo will pass through the new route annually.
The current state of infrastructure requires attention: a quarter of all railway lines in the country are already operating at their limit, while another 15% are overloaded.
Modernization and Construction Plans
To prepare for new loads, the government intends to implement a series of large-scale projects through 2030. The main focus is on track electrification and the construction of new sections.
Target Indicators by 2030
Implementation Stages
- April
Work begins on laying the second track on the Tukimachi–Angren section
- 2025
Completion of the Tashguzar–Kumkurgan section modernization and electrification of the Andijan–Khanabad and Kumkurgan–Kudukli directions
- 2027
Modernization of the Angren–Pap line and consideration of constructing a second track
The President called on international investors and financial organizations to participate in the financing and implementation of these infrastructure projects.