GenerationPartially operating
Камбар-Атинская ГЭС-2in Russian
Jalal-Abad Region
- Design capacity:
- 360 МВт (3 × 120 МВт)in Russian
- Financing:
- ЕФСРin Russian
- Construction started:
- 1986
- Unit 2 planned launch:
- 2029
A registry of 32 projects: roads, railways, generation and power grids, gas and airports. Each has a status from the latest source found, dates as stated in documents, financing with loan terms and coordinates with their precision.
Data as of October 6, 2026
Showing 2 of 32
2 projects · coordinate precision is listed below the map
Jalal-Abad Region
Issyk-Kul Region