In Suusamyr village, located in the Jaiyl district, an active phase of infrastructure renewal is underway. The construction of the local community center, which began in 2019 with state budget funding, is almost complete. Currently, specialists have completed 90% of the planned work.

To complete the facility, interior finishing, heating system installation, and landscaping of the area are required. Additionally, renovation of the K. Konushbaev secondary school is underway in the village. According to the schedule, the work, which started on July 24, 2026, is expected to be finished by November 1, 2026.

Construction and renovation indicators

95%of K. Konushbaev school renovation
90%of community center readiness
200seats in the new community center
570square meters of the community center area

Medicine and education in Kyzyl-Oy

In Kyzyl-Oy village, the educational process continues in the main school building, as a fire occurred in the old building in November of this year. Currently, the educational institution accommodates 134 students.

During the inspection, the General Practice Center in Suusamyr was also visited. The medical facility, consisting of a building constructed in 1960 and a new building from 2014, is equipped with necessary medical equipment and a 15-bed inpatient ward.

Context

Ulan Mamatkanov is the Deputy Chairman of the Cabinet of Ministers of the KR. The inspection covered facilities in the Jaiyl district of the Chui region, which has a population of over 92,000 people.