The Chui Regional Administration of the State Architectural and Construction Control Department under the Ministry of Construction conducted a quality inspection of road works on the Chapaev — Kegeti — Arpatekir section. Inspectors established that the laying of the asphalt concrete pavement on the 3.2-kilometer stretch does not comply with construction norms and technical requirements.
Fine and rework
Following the inspection, an official report was drawn up against the contractor, Dol Nur LTD LLC, and an order to rectify the defects was issued. The organization was fined a significant amount.
200 000 som fine imposed on
contracting organization Dol Nur LTD LLC
At this moment, the company has already dismantled the asphalt that failed the inspection. Re-work is currently underway on this section, being carried out in compliance with all technological standards.
Context
The inspection was conducted on a highway in the Chui region, which had a population of more than 1.1 million people as of 2020.