The large-scale reconstruction at Osh Airport aims to increase capacity and enhance flight safety. In addition to the new terminal construction, works will cover the runway, taxiways, and aircraft parking zones.
New Terminal and Parking
According to Timurlan Madanbekov, Director of the Osh branch of Manas International Airport OJSC, the total area of the new terminal will exceed 25,000 square meters. Currently, builders have completed the main building frame, roofing, and external utility connections. Specialists are now working on installing internal partitions and stained-glass structures.
For the convenience of passengers and visitors, a parking lot with a capacity of 600 spaces is also being constructed on the airport grounds.
Runway Modernization
A key element of the upgrade will be the modernization of the runway. The project provides for its extension and pavement reinforcement, which will allow for the reception of heavier and more modern aircraft types.
As a result of the works, the runway length will increase from the current 2,200 meters by 400 meters, reaching 2,600 meters. The top asphalt surface will also be renewed, increasing the Pavement Classification Number (PCN) from 44–50 to 72.
Accelerating Flight Turnaround
To optimize aircraft movement, the construction of three additional taxiways is planned. This will allow liners to vacate the main runway more quickly after landing.
Previously, it took 8-10 minutes from aircraft landing to exiting onto a taxiway and vacating the main runway. The construction of new paths will reduce this time and significantly increase the airport's capacity.
Additionally, as part of the project, extra land plots have been allocated to increase the number of aircraft parking stands, which were previously limited to 12 units.