The new aviation complex is being built in Suzak district of Jalal-Abad region. The project provides for a modern international airport that will operate under international category 4E, allowing it to handle large aircraft, including Boeing and Airbus.

Key specifications and project timelines

Construction began in May 2025. A total of 381 hectares of land was allocated for the airport in the Bagysh ayil aimak.

3,800runway length
350passengers per hour
60 millionpreliminary cost

The project includes the construction of a 3,800-meter runway and a three-story passenger terminal. According to the latest plans, construction is scheduled for completion in Q3 2027.

What this means for the region

The new airport is intended to replace the existing facility, which is located within urban development and has constraints that hinder further development. Kyrgyzstan Airports OJSC clarified that the preliminary construction cost of about 60 million dollars may change after the work is completed and financial calculations are carried out.