The Water Resources Service has initiated a procurement for construction and installation work on the second stage of the daily regulation basin on the Chanach-Sai River. The procurement is being conducted as part of a project adjustment, and according to the public procurement portal, the planned amount is 1 billion 823.4 million som.
Requirements for participants and technical equipment
- The participant must confirm experience in the construction of hydraulic and irrigation structures worth at least 1.824 billion som in the period 2024–2025.
- The general contractor must have commissioned at least two daily regulation basin facilities with an area of at least 800,000 square meters during the specified period.
- Confirmation of access to financial resources in the amount of at least 100 million som is required.
- The participant must hold a level II license for hydraulic engineering construction and irrigation structures and must not have had losses over the past year.
Equipment and guarantees
- The technical equipment for the work is subject to the following requirements: 12 dump trucks with a capacity of 25 tonnes, 10 dump trucks of 10 tonnes each, 5 bulldozers with a capacity of 130 hp, 5 tanker trucks, as well as a mobile concrete mixing unit and other machinery.
Financial parameters of the tender
The procurement sets the following guarantees: the bid security is 1%, and the performance security is 1%. The warranty period after the facility is commissioned will be 1 year.