The construction of a new small hydropower plant in the Issyk-Kul region will become part of the republic's program to increase energy capacity. As Ermek Bakhavadinov, the akim of the Jeti-Oguze district, reported, the project has already passed key preparatory stages.

Financing and generation volumes

The investment project is being implemented by Bishkek Stroy Konstruktsiya LLC under the leadership of Aibek Sulaimanov. The Russian-Kyrgyz Development Fund is participating in the financing. The total investment in construction will amount to $7.5 million.

25 millionkWh of electricity per year
$7.5 milliontotal investment amount
$2.34 millionown funds
$5.46 millionborrowed funds
5.5hectares of leased land

Preparatory work

At the moment, topographic and hydrological studies have already been conducted for the project implementation, and a feasibility study and engineering survey report have been prepared. A land plot of 5.5 hectares has been leased for construction.

All necessary permits have also been obtained: positive conclusions from the state environmental expertise, documents related to forestry, and urban planning documentation. The HPP working project, developed with the participation of international consultants, has also received approval from the state expertise.