The launch of heating systems in Kara-Kul, located in the Jalal-Abad region, began due to a sharp decrease in air temperature. The main task of the current work is to ensure uninterrupted heat supply to citizens and social institutions in the upcoming autumn-winter period.

Boiler plant launch schedule

The process of launching utility systems is carried out in stages according to the approved schedule. First, the coal-fired boiler plant was prepared, after which the operation of electric capacities will begin.

  1. November 10

    Ketmen-Töbö coal-fired boiler plant switched to full operating mode

  2. November 11

    start of the phased commissioning of city electric boiler plants

Scale of heat supply

Heat supply covers a significant part of the city's population. Currently, the number of consumers of the services provided by the enterprise responsible for heating the city is:

Previously, city residents had repeatedly expressed concern on social media regarding the start dates of the heating season.