The pace of road construction in the region was discussed at an expanded meeting of the Jogorku Kenesh Committee on Finance, Budget, Entrepreneurship, and Competition Development. Minister of Transport and Communications Talantbek Soltobaev reported that work on the 46-kilometer stretch of the Naryn—Baetov road will only begin next year.
Status of works on the Naryn—Baetov highway
According to the ministry, the total length of the road is 125 km. Some sections are already fully completed, while work on others is still in progress.
Road parameters
Committee Chairman Kubanychbek Samakov expressed dissatisfaction with the long implementation period of the project. In his view, no results have been achieved after ten years of work, and completion could take another five years.
"In short, 10 years have passed, and you won't finish for another 5 years"
Problems on the On-Archa—Zhany-Talap section
Additional questions arose regarding the 9-kilometer On-Archa—Zhany-Talap section. The MP reminded that two months ago the ministry promised to lay the first layer of asphalt, but to date, the work has not been completed despite the allocated funds.
The Transport Minister explained that earthworks have already been completed on 4–5 km of this stretch and 1 km of asphalt has been laid. Under favorable weather conditions, they plan to extend the pavement to 3–4 km and complete the rest next year.