The first hydropower unit of Kambarata HPP-2, which has been functioning since 2010, is unable to transmit the full volume of generated energy into the grid. The main reason for the constraints is the condition of the power transmission lines, which cannot handle the high load.
Technical constraints and power losses
As reported by First Deputy Minister of Energy Kursantbek Omurbekov on Birinchi Radio, the existing infrastructure does not allow the equipment to be utilized at 100%. Due to the inability to pass the full volume of current through the networks, part of the generation is effectively lost.
Modernization and construction plans
To address the capacity deficit and grid aging, a new project is planned. Specifically, it involves the erection of a second hydropower unit and the construction of a new 500-kilovolt substation, which will allow for the transmission of additional volumes of electricity.
- 2010
launch of the first hydropower unit of HPP-2
- February–March 2027
planned start of construction for the second unit
According to the Deputy Minister, design work is already in its final stages. Contracting organizations and funding sources for the project implementation have already been identified.