According to the announcement published on November 27, 17,082,254 som will be directed toward the project's implementation. The works will cover an area of 4,395 square meters, which must first be completely cleared.

Stages and volumes of work

The initial stage includes the demolition of the old surface and preparation of the base. The specification states that the contractor will have to dismantle 11.06 cubic meters of concrete foundations, remove 62 cubic meters of 10 cm thick asphalt concrete, and dismantle 147 meters of curbs. It is also planned to remove more than 1.4 thousand tons of construction waste and soil.

Surface area by type

1995sq. m for asphalt
980sq. m for paving stones
600sq. m for rubber coating
820sq. m for lawn

New asphalt concrete with a thickness of 4–6 cm will be laid on a two-layer sand and gravel base for driveways and parking zones. Pedestrian areas will be decorated with colorful paving stones covering an area of 980 square meters.

Infrastructure and landscaping

In addition to the road surface, the project provides for the renovation of the irrigation system and the creation of recreation areas. In particular, the installation of 140 meters of drainage gutters with metal grates and the mounting of 46 meters of 200 mm diameter pipes are planned.

  • Planting 24 birch trees 3–3.5 meters high
  • Development of children's and sports areas with rubber coating
  • Installation of an automatic watering system with a pump and 40 sprinklers
  • Adjustment of seven cast-iron manhole covers

17082254 som

planned procurement amount