The main stage of work on the strategic Barskoon-Bedel highway is scheduled for 2029. As Chairman of the Cabinet of Ministers and Head of the Presidential Administration Adylbek Kasymaliev reported during a Jogorku Kenesh (parliament) meeting, the full opening of the road is planned for 2030.

StoriesBarskoon-Bedel highway to open in 2030Slides: 6
  1. Barskoon-Bedel highway to open in 2030
  2. August 27, 2025 — Construction of the 161.4 km road began; 2029 — Main stage of work is scheduled to be completed; 2030 — Full traffic operations are expected
  3. Project scale: 50 bridges to be built; Two tunnels: Sook and Ashuu-Suu
  4. 1700 workers — involved in the highway construction
  5. 814 units — of special equipment at the site
  6. Other transport updates. The Kok-Art tunnel reduced travel time from Jalal-Abad to Balykchy from 13 to 6 hours.

Construction scale and transport infrastructure

Tunnel excavation work is currently underway at the site. The project requires significant resources for implementation.

1,7 thousandworkers
814units of special equipment

In parallel, other transport directions are being developed across the country. In Bishkek, the 33.4-kilometer northern bypass road has been expanded, and construction of a 16-kilometer eastern bypass is underway. Additionally, summer traffic has opened through the 3.9-kilometer Kok-Art tunnel on the alternative North-South road, reducing travel time from Jalal-Abad to Balykchy from 13 to 6 hours.

Rail and air communications

Significant changes have also affected other modes of transport. The Balykchy—Kochkor railway began operations on July 25 and has been used since October to transport coal from Kochkor to Bishkek. More than 10,000 specialists are involved in the construction of the China—Kyrgyzstan—Uzbekistan highway.

In the aviation sector, the Airports of Kyrgyzstan company has allocated 9.4 billion som of its own funds toward infrastructure modernization. Thanks to these measures, the updated Manas Airport resumed operations until August 31. It is also noted that on June 9, 2026, Kyrgyzstan was removed from the EU aviation safety list.

Context

Construction of the 161.4 km Barskoon—Bedel road began on August 27, 2025. The project involves the construction of 50 bridges and two tunnels—Sook and Ashuu-Suu. The contractor is the China Road and Bridge Corporation (headquartered in Beijing).