In the Issyk-Kul region, construction continues on a 14.5-kilometer section of the Boz-Uchuk – Shakhta – Jyrgalan highway. Work is being carried out on one of the key routes providing access to the Jyrgalan Valley and the Ala-Too Resort ski resort.

Current status of works

According to the press service of the Ministry of Transport and Communications, 62% of earthworks have been completed to date. On certain sections of the route, builders have already begun laying the road surface.

Construction indicators

14.5km section length
62%earthworks completed
700meters of asphalt laid
100units of machinery
130workers

According to the agency, retaining walls and culverts have already been installed on the main road as part of the project. The first layer of asphalt has been laid on a 700-meter section.

Context

Construction is being carried out in the Issyk-Kul region, which, according to 2025 data, has a population of 549,800. The Boz-Uchuk – Shakhta – Jyrgalan road is an important transport route for tourists visiting the Jyrgalan Valley.