According to the Ministry of Construction, construction and installation works resumed at the Kudaybergen and Shopokov Eco City residential complex sites on September 1. Previously, due to the suspension of construction by the company Dooolot Kurulush, thousands of citizens were unable to receive their promised housing.
Current status of work at the sites
At present, a significant number of specialists are deployed at the Kudaybergen construction site. Work is being carried out in various directions depending on the specific building:
- In building No. 2, the fifth floor is being constructed
- In building No. 3, excavation work for the pit is underway
- In buildings No. 5 and 8, dismantling of old formwork and preparation for continued work is in progress
- In buildings No. 6, 7, 9, and 10, foundation installation has begun
The Ministry of Construction carries out daily monitoring of work quality and compliance with construction norms and safety regulations. The agency's main task is to ensure the high-quality completion of the project and the handover of apartments to equity holders.
Context
The problem with the Dooolot Kurulush company sites persisted for several years. To resolve the issue, by order of the president in February 2026, a 99% stake in the firm was transferred to the construction directorate under the Ministry of Construction and registered in the state registry.