The implementation of the project has prepared the infrastructure for potential electricity exports. According to First Deputy Minister of Energy Kursantbek Omurbekov, exports will be carried out using surplus resources remaining after meeting the country's domestic needs.

Project Essence and Reasons for Delays

The CASA-1000 project involves connecting the energy systems of Kyrgyzstan and Tajikistan with Afghanistan and Pakistan. This will be made possible through the modernization of the power grid complex, the construction of new substations, and the installation of high-voltage power lines.

As Omurbekov explained, delays were observed during the implementation process. This was due to the suspension of construction works in Afghanistan following the change of power there.

"We have fully fulfilled our obligations under CASA-1000. Construction works are complete"
Kursantbek Omurbekov, First Deputy Minister of Energy of the Kyrgyz Republic

Context

The project is aimed at exporting electricity during the summer period. Previously, on March 31, 2025, Presidents of Kyrgyzstan Sadyr Japarov and Tajikistan Emomali Rahmon launched the 500 kV "Datka–Sugd" line in the city of Khujand.