The investment aims to upgrade power lines and substations to improve electricity transmission and reduce the risk of equipment overload. According to Kursantbek Omurbekov, the First Deputy Minister of Energy, the current wear and tear of air lines and substations hinders efficient delivery to consumers.

Infrastructure upgrades and grid connection

The planned works include building a new 500 kV substation, which will be integrated with the existing 'Frunze' and 'Kemin' 500 kV substations. Additionally, the project involves connecting substations with voltages of 220 kV and 110 kV.

The Deputy Minister emphasized that increasing generation capacity alone is insufficient to solve electricity shortages. Modernizing the transmission lines and substations is essential because outdated infrastructure limits the ability to deliver produced electricity to the population.

Context

The plans for a new substation were previously announced by Minister of Energy Altynbek Rysbekov on July 21, 2026, following electricity outages in Bishkek and the Chuy region during periods of high temperatures.