During a Jogorku Kenesh meeting on November 18, Prime Minister Adylbek Kasymaliev detailed the ongoing efforts to increase electricity generation across Kyrgyzstan through hydropower modernization and solar energy development.

Hydropower modernization and new plants

A major milestone was reached with the completion of the comprehensive rehabilitation of the Toktogul HPP in the Jalal-Abad region. This project has successfully increased the station's capacity.

Ранее по темеKyrgyzstan targets 8% economic growth and increased social spending by 2030

Key energy capacity figures

1,440MW capacity of Toktogul HPP
35small HPPs opened since 2025
20.3MW total capacity of 6 new small HPPs
216planned MW for Uch-Kurgan HPP

The government plans to commission the Orto-Tokoy HPP by the end of 2026, following its successful technical launch. Additionally, six small hydropower plants with a combined capacity of 20.3 MW are expected to be operational by the end of this year. Modernization efforts are also underway at the Uch-Kurgan HPP in the Nooken district, where capacity is set to rise from 180 to 216 MW by late 2026.

Large-scale projects and solar energy

Regarding major infrastructure, construction of a second 120 MW unit at the Kambarata HPP-2 is ongoing, with completion targeted for 2028. Meanwhile, intergovernmental negotiations for the Kambarata HPP-1 project continue after three rounds of talks.

Under the support of President Sadyr Zhaparov, the country is also expanding its solar footprint. Recent developments include the opening of a 100 MW solar plant in the Kemin district, a second large plant in Toru-Aigyr, and the Bishkek solar power plant. Furthermore, the first phase of renewable energy facilities with a capacity of 175 MW has been launched.

  1. 2025

    Completion of Toktogul HPP rehabilitation

  2. 2025

    Opening of 35 small HPPs

  3. End of 2026

    Expected commissioning of Orto-Tokoy HPP and Uch-Kurgan HPP modernization