Construction of a sewerage network is being prepared to connect new buildings in the Kozhomberdieva Street area. The project will affect the territory of the Kara-Balta City residential complex currently under construction, with BayEl Building LLC serving as the contractor. According to the Ministry of Justice, Myktybek uulu Belek is the founder and head of this company.

Utility Parameters and Conditions for Commencement of Work

Work will begin once detour routes for the construction period are determined and technical details are coordinated with utility services. The list of organizations requiring coordination includes the thermal power plant, the water utility, Kyrgyztelecom, the electric grid service, and other agencies.

According to preliminary data, laying the pipes will require digging trenches with the following characteristics:

3trench width (m)
2–2.5trench depth (m)
500pipe diameter (mm)

Scale of the Residential Complex

Construction of Kara-Balta City on an area of 33 hectares began on February 21, 2025. As previously reported by Kanaybek Tumanbaev, head of the Presidential Administration's Management Department, this is the first time in a long while that multi-story buildings meeting modern standards are being erected in the city.

60blocks (buildings)
4,420apartments
750school seats
280kindergarten seats