Hydro unit No. 1 has been commissioned at the Uch-Kurgan HPP, marking the final of the four units to undergo large-scale upgrades. The startup process was overseen by Ulugbek Mamyraliyev, General Director of OJSC Electric Stations.
Growth in production indicators
As a result of the works, the station's total capacity increased by 36 MW. During 2026, company specialists upgraded two units simultaneously — No. 1 and No. 2. The Ministry of Energy noted that this modernization marks the first large-scale upgrade of the station's main equipment in over 60 years of operation.
Station capacity indicators
According to the ministry, the expanded electricity generation capacity will ensure the efficient operation of this strategic hydropower facility and support the stability of the country's power system during the upcoming 2026–2027 autumn-winter season.
Context
The Uch-Kurgan HPP is located in the Jalal-Abad region on the Naryn River. The facility was commissioned in 1961–1962.