According to the press service of the President's Plenipotentiary Representative in the Batken region, the project involves building retaining walls to secure the area against mudflow threats.
Project scale and progress
The construction is being carried out by the Batken Mobile Mechanized Detachment, a state enterprise under the Ministry of Emergency Situations of the Kyrgyz Republic. Currently, 350 meters of the retaining wall have been completed.
Baktybek Toksonbaev, the First Deputy Plenipotentiary Representative of the President in the Batken region, inspected the progress of the construction works. The project is scheduled to be finished by December 25.
Context
The works are taking place in Ak-Tatyr, located within the Batken district of the Batken region.