According to the press service of the President's Plenipotentiary Representative in the Batken region, the project involves building retaining walls to secure the area against mudflow threats.

Project scale and progress

The construction is being carried out by the Batken Mobile Mechanized Detachment, a state enterprise under the Ministry of Emergency Situations of the Kyrgyz Republic. Currently, 350 meters of the retaining wall have been completed.

2542total length of walls (m)
8616total mudflow channel length (m)
6074upper part of the channel (m)
350meters completed

Baktybek Toksonbaev, the First Deputy Plenipotentiary Representative of the President in the Batken region, inspected the progress of the construction works. The project is scheduled to be finished by December 25.

Context

The works are taking place in Ak-Tatyr, located within the Batken district of the Batken region.